City of Madison Wastewater Collection System

City of Madison Wastewater Collection System

Madison, IN

Delivery Method: Design Bid Build
Project Size: 1.25M Gallon Concrete Wet Weather Storage Facilities
Construction Value: $10.59 M

21

month long project for the City of Madison Collections System, as well as the Wastewater Utility which scope included multiple locations and structures, as well as 10,000 + LF of UG gravity sewer and force main piping installations.

1

part of the long term control plan. Thieneman also built Division B which was a small chemical building project at the Water Pollution Control Facility in Madison ($ 600,000).

1

of the lift station upgrades as well as several thousand feet of sewer and Force Main were along Vaughn Drive which is right next to the Ohio River!
The project included improvements to the City of Madison’s existing wastewater collection system to provide adequate transport and storage during wet weather events. The work included construction of two (2) concrete wet weather storage facilities (750,000 gallons and 500,000 gallons) with automatic flushing/cleaning systems, three (3) new wet weather lift stations (4.6 MGD, 3.0 MGD, and 1.0 MGD), installation of 12” and 16” gravity relief sewers, installation of new 8”, 12”, and 14” dia. Force mains, and the replacement of a section of existing 12” diameter gravity sewer.